Module 9: Project contractual structure, rights and obligations
The Bill of Quantities (BOQ) is used in a remeasurement contract, and normally specifies:
The BOQ is updated periodically (normally monthly) to show the actual quantities of work undertaken by the contractor to date.
The BOQ will be finalised at the completion of the project to show the actual final quantities of work undertaken by the contractor.
Periodic (e.g. monthly) and final payment to the contractor will be based on the BOQ.