Module 3:  Common types of corruption in project procurement

Abuse of procurement procedures - Examples 5

Bid documents enable corrupt variations or price adjustments

A procurement manager or design engineer may ensure that the bid documents are written in a manner which allows corrupt variations or price adjustments during construction phase.  For example:

  • The bill of quantities (BOQ) may specify a small quantity of components in one category when the likelihood is that the quantity will be materially increased after contract award.  This fact will be communicated to the corruptly pre-selected bidder enabling it to put a high price on that component, resulting in significant profit once the variation is instructed.
  • The conditions of contract may remove the requirement for a unit rate adjustment in the event of material change of BOQ quantities, or remove the requirement for a re-bid of a major variation, resulting in a windfall profit for the winning bidder.

Abuse of emergency or other exemption procedures

Procurement regulations may allow exemption from competitive procurement in cases of emergency (e.g. natural disaster) or if a product is unique.

This exemption may be abused by a procurement manager or public official so as to enable corrupt selection of a bidder.  For example:

  • In the case of a genuine emergency, it may be possible to obtain competitive bids under an expedited timetable, but the procurement manager may corruptly place a contract at a high price without a competitive process.
  • The emergency or exempt situation may be artificially created:
    • by delaying an action until it becomes an emergency,
    • by falsely declaring an emergency, or
    • by falsely stating that there is only one possible product or seller.